The project’s power and utility buildings are consolidated in an area along the west boundary of the site and accessed via St Brendan’s Way, which will be one of the main thoroughfares through the TU Dublin campus. These buildings include the Energy Centre, the Electrical Substation, and possibly the Wood Chip Storage and the composting area.
An interim Energy Centre is being constructed to service the Central and East Quads which are due to open in September 2020. This phase is due for completion in November 2019
Programme
Planning for Energy Centre was approved by Dublin City Council in December 2017.
Procurement Route
This project has been developed through the Masterplan Team (MRY).
Design Team
O’ Connor Sutton Cronin through MRY
Contractor
John Paul Construction – interim Energy Centre
Alternative Heat – interim Energy Centre
- Environmental Monitoring Reports
As part of the construction works for the interim Energy Centre at Grangegorman, environmental monitoring will carried out to assess the dust, noise and vibrations arising from the works. They will be published as they become available on this page.
Dust, Noise Vibration Reports
Interim Energy Centre Monitoring Report 18th July – 2nd Aug